Reshna Begum — Backyard Renovation

Also known as: Project Reshna

The Problem: A Collapsed Roof and a Cold Home

Reshna Begum, a 35-year-old woman living in Hasanpur village in Moulvibazar, was facing a severe housing crisis. Her husband, who was blind, was completely unable to work or perform manual labor. The family had also suffered the immense emotional tragedy of losing four children at birth. To make matters worse, the front porch roof of their tin house had completely collapsed due to heavy rains, leaving the interior of their home exposed to constant flooding, dampness, and cold winds.

They lived in a shared house with Reshna's father-in-law and brother-in-law's family, but neither household could afford the materials or labor to repair the structure. The safety and health of this vulnerable couple were at critical risk as winter approached.

The Field Verification & Execution

Our Moulvibazar regional coordinator, Rabbi Miah, conducted a field visit to inspect the damage, verify the costs, and coordinate the repairs. On November 2, 2024, We Do Charity launched the fundraiser with a target of 21,000 BDT. Thanks to our donor community, we collected a total of 23,400 BDT. After deducting the bKash cashout fee of 300 BDT, we had a net total of 23,100 BDT to fund the construction.

Itemized Materials & Financial Transparency

True to our commitment to showing where every single Taka goes, we published the complete construction expense breakdown. The total cost of the project came to 23,970 BDT. The minor deficit was covered directly from our collective emergency fund:

  • Tin Sheets (Corrugated iron): 13,820 BDT
  • Wood (Structural posts & frames): 4,600 BDT
  • Iron, Rope & Wire: 850 BDT
  • Tin Transport: 450 BDT
  • Wood Transport: 450 BDT
  • Labor Costs (Carpenters/Builders): 3,000 BDT
  • Labor Meals (Provided to workers): 300 BDT
  • Direct Cash Gift to Reshna: 500 BDT

The construction was completed on November 9, 2024. The porch roof was rebuilt from scratch with new, heavy-duty posts and waterproof corrugated tin sheets. The direct cash gift of 500 BDT allowed Reshna to buy fresh food items. When the keys were handed back, Reshna was overwhelmed with tears of joy, knowing her home was safe from the elements.

Frequently Asked Questions

Q: Who managed the backyard renovation on the field?

A: Our regional coordinator, Rabbi Miah, personally managed the procurement of materials, hired local carpenters, and supervised the renovation.

Q: How did WDC cover the cost deficit?

A: The total spent was 23,970 BDT, which exceeded our net collections by 870 BDT. This difference was covered using the organization's central emergency reserve.

Q: What other home repair projects has WDC completed?

A: This was our first construction project, paving the way for larger shelter initiatives like Project 11: Tara Banu's House Repair and Project 17: Rahela Chachi's House Construction.

The Impact

Porch roof fully repaired. Reshna overwhelmed with emotion. WDC slightly over-spent (covered from fund).

Beneficiary Spotlight

"~35 years old. Husband blind and unable to work. Lost 4 children at birth. Porch roof collapsed, flooded during rain. Living in shared house with father-in-law and brother-in-law's family."

Reshna Begum (individual)

Financial Transparency

Expense ItemCost (BDT)
tin sheets13,820
tin transport450
iron rope wire850
wood4,600
wood transport450
labor3,000
labor meals300
cash gift to reshna500
Total Spent23,970

Media Gallery

Reshna Begum — Backyard Renovation - Gallery Media 1
Reshna Begum — Backyard Renovation - Gallery Media 2
Reshna Begum — Backyard Renovation - Gallery Media 3
Reshna Begum — Backyard Renovation - Gallery Media 4
Reshna Begum — Backyard Renovation - Gallery Media 5

Project Facts

  • Target Amount

    21,000 BDT

  • Funds Raised

    23,400 BDT

  • Beneficiaries

    Reshna Begum (~35 years old) — husband blind and unable to work, lost 4 children at birth, living in house with collapsed tin roof porch

  • Location

    Hasanpur village, Chandnighat Union, Moulvibazar Sadar Upazila

  • Timeline

    2024-11-02 → 2024-11-09